Brioni / Bruton St, London

Project Size: 9000 sq ft.

Duration of Project : 24 weeks

brioni-feature.jpg
Anchor 1

This 9,000 sq ft project was carried out over 24 weeks in five Separate phases over 6no. Floors due to the client’s requirements to continue trading.

​

The store was completely re-wired from top to bottom and CBL were involved in the design process. The systems covered in this install were as below;

​

  • Distribution & Metering

  • Lighting Install & Lighting Control System

  • Emergency Lighting

  • Small Power

  • Data Install

  • CCTV / Intruder Alarm / Access Control

  • Fire Alarm System